Case Study 8

Automation of Water Treatment Plant

REQUIREMENT

Centrally managed fully automated system for two pre-treatments and multiple storage and distribution networks.(RO, UF, WFI&PW Distribution)

  • Control, monitoring and alerting of critical process parameters
  • 21CFR Complaint System

AUTOMATION SOLUTION PROVIDED

  • S7-1200 system with IO Modules for each Station.
  • TP1500 with Panel Audit license and connected centrally to the redundant SCADA server.
  • Central Redundant SCADA Operator station
  • Engineering Station with all the required engineering software’s.
  • 21CFR compliant system with all audit and electronic records.
  • Documentation as per GAMP guidelines.