Automation of Water Treatment Plant
![](https://qv5ec2.n3cdn1.secureserver.net/wp-content/uploads/2022/12/Blog-image_inner_8.jpg)
REQUIREMENT
Centrally managed fully automated system for two pre-treatments and multiple storage and distribution networks.(RO, UF, WFI&PW Distribution)
- Control, monitoring and alerting of critical process parameters
- 21CFR Complaint System
AUTOMATION SOLUTION PROVIDED
- S7-1200 system with IO Modules for each Station.
- TP1500 with Panel Audit license and connected centrally to the redundant SCADA server.
- Central Redundant SCADA Operator station
- Engineering Station with all the required engineering software’s.
- 21CFR compliant system with all audit and electronic records.
- Documentation as per GAMP guidelines.